Testing finds highly corrosive environment no match for FRP

Testing on structural members installed in a highly corrosive marine environment have shown that Wagners Composite Fibre Technologies (CFT) pultrusion maintained its structural strength and continued to meet design values after more than a decade in service.

Cameron Rocks fishing and viewing platform located on the Brisbane River in Hamilton, Queensland posed significant durability challenges for Brisbane City Council due to strong tidal water cycles, highly corrosive salinity and UV exposure. 

Pictured - Cameron Rocks is located in Hamilton on the Brisbane River.

In 2009 the old, corroded metallic project was replaced with a more durable Fibre Reinforced CPolymer (FRP) structure.

Wagners CFT LeadStructural Engineer, Dr. Ali Mohammed said twelve years on from project completion and major flooding in 2011, several members were removed for durability investigations and replaced with new ones as part of Wagners CFT’s ongoing Research and Development work.

“Several coupons were cut out from the obtained samples for physical and mechanical testing including interlaminar shear, compressive and flexural strength,” Ali Mohammed said.

“With the interlaminar shear strength under standard ASTM D2344 our test produced a 50.15 MPa result which is in excess of Wagners QA pass mark of 50 and well above the design value of 44,” Dr Mohammed said.

“Meanwhile with the Compressive Strength test under standard ASTM D6641 we achieved a 520.78 MPa result, which again is well above Wagners QA pass mark of 500 and the design value of 485,” he said.

“Finally Flexural Strength testing under standard ASTM D79 produced a result of 890.08 MPa, which is greater than Wagners QA pass mark of 800.”

Barcol hardness testing was also undertaken.

“Barcol hardness was also carried out on the obtained samples and compared with controlled samples and the current QA passmark to evaluate the paint and surface properties,” Ali Mohammed said.

“What we found was that the samples still met the requirements with a slight increase in value which could be attributed to additional curing overtime,” Dr Ali Mohammed said.

“These results really reflect the excellent durability performance of Wagners FRP composites as it demonstrates its high mechanical strength and endurability despite challenging environments which ordinarily would significantly impact the performance of more traditional materials in the same time frame,” he said.

“The results were not a surprise for Wagners because all products are rigorously tested in accelerated durability lab experiments; but what these tests do confirm for us in real life applications is that the verified laboratory simulations are accurately predicting the performance and design life of the members.”
The team reviewed results against water quality in the Brisbane River captured through the Brisbane Airport Water Quality Report from 2002 - 2005.

“From 2002 to 2005 salinity results for the Brisbane River near Cameron Rocks fluctuated around 34g/L; which is in line with what you would expect to see as an average in seawater especially given this area is near the mouth of the river,” Ali Mohammed said.

“As we saw with the structure which was replaced in 2009, corrosion of reinforcing steel and other ferrous metal is one of the biggest causes of deterioration in coastal construction projects,” Dr Mohammed said.

“Certainly in a twelve year period should we have built that structure with metal again instead of FRP I expect that we would have found similar results to the structure which was replaced in 2009 because the bacteria in ocean water consumes iron and their excretions turn to rust making metal projects problematic from a sustainability/durability point of view,” he said.

Wagners FRP is one of the lightweight structures commercially available and well known for high performance in high-stress and chemical environments.

“The state of the art design and manufacturing of Wagners FRP composites delivers exceptional chemical and mechanical properties that can withstand harsh environments,” Ali Mohammed said.

“Our FRP sections are used in various applications ranging from high-stress, electric and thermal environments like electric poles to support structures for construction industries,” Dr Mohammed said.

“The high fibre volume fraction allows our composites to withstand extreme conditions without demonstrating any failures,” he said. 

“The fact that these members are manufactured here in Australia, to Australian standards for Australian conditions also certainly goes a very long way to ensuring that structures constructed from these members will perform beyond expectation and showcase exceptional durability.”

To view Wagners CFT’s range of products and better understand the performance advantages of construction with FRP visit Product Guide

Share this article:


More stories to explore:

by Kellie Stewart 12 May, 2024
Electricity distribution company, Essential Energy, partners with EV charging company, EVX and Australian manufacturer of Fibre Reinforced Polymer (FRP) structural profiles, Wagners Composite Fibre Technologies (CFT) to trial a streetlight Electronic Vehicle (EV) charger – a new concept for delivering low-impact, accessible EV charging in regional NSW. The prototype streetlight EV charger has been installed in the Mid North Coast town of Port Macquarie to trial an innovative way to increase charging options for residents and visitors to regional, rural and remote communities. The streetlight charger connects to the existing electricity used to power the streetlight, eliminating the need to install additional infrastructure and undergo major earthworks, which is typical for EV charging alternatives, reducing the visual and environmental impact. Due to their convenient location near the curb adjacent to car parking spaces, streetlights have the potential to play a significant role in expanding public ‘top-up’ charging facilities in regional NSW. Essential Energy Chief Commercial Officer Justin Hillier says the trial is using a prototype composite streetlight column with a cavity designed to completely house an EV charger. “Essential Energy has been working in partnership with Wagners CFT and EVX to develop a product that provides a faster and easier way to roll out more EV charging. The innovation of the streetlight EV charger also provides the opportunity for people who live in housing that can’t be retrofitted with charging facilities to purchase EVs, as well as offering top-up charging for tourists and locals. Enabling more options for charging across the Essential Energy network is part of our commitment to facilitating the uptake of electric vehicles.” EVX CEO, Andrew Foster, believes the proof of concept will be great news for local councils across NSW. “By combining innovative technologies with public infrastructure, this new approach to deploying much needed EV chargers allows councils to roll out new public EV chargers easily and cost-effectively at scale and in convenient locations. Importantly, the ability to utilise pre-existing infrastructure instead of adding new electrical assets to the streetscape is anticipated to make it easier for councils to navigate crucial planning considerations, especially when it comes to assessing the public impacts of expanding EV charging capabilities.” Wagners CFT Australia/New Zealand General Manager Ryan Leeson says they look forward to seeing the results of this innovative trial. “As the uptake of electric vehicles and demand for charging increases, Wagners is excited to be partnering with Essential Energy to produce a solution for EV customers that leverages existing infrastructure, is low impact, and uses Wagners proven composite technology in the form of a streetlight column.” Members of the public are encouraged to use the streetlight EV charger, which is free-of-charge, and to provide feedback during the four-week period via a QR code on the side of the column. The streetlight EV charger is located near 1 Clarence Street, Port Macquarie and is available for use until 10 June 2024.
by Kellie Stewart 26 Apr, 2024
Upgrading an old timber boardwalk in an ecologically important mangrove forest that is home to several threatened species and feeds into an internationally recognised marine park is no mean feat! But it’s a challenge like this that New South Wales based Indigenous civil construction company ALI Civil love to take on and pride themselves on successfully delivering. Director Cohen Jirgens said Huskisson Mangrove Boardwalk had reached the end of its useful life but its replacement posed significant challenges to the sensitive environment in which it sat. “The Huskisson Mangrove Boardwalk is located in the Jervis Bay Marine Park in New South Wales Australia and was originally constructed in 1991; and at that time it was 300 metres long and constructed from treated soft and hard woods,” Cohen Jirgens said. “Actually one of the original members of the construction team provided us with some details of the original build including the total cost which was $37,000 for both labour and materials; that works out to be $123 dollars a lineal metre which is totally inconceivable today,” Mr Jirgens said. “Since its construction in 1991, the boardwalk has been a major drawcard for the community of Huskisson attracting tens of thousands of people to gently meander through the established mangrove forest on the tidal mudflat of Currambene Creek,” he said. “And when the tide floods in, the mangroves come to life with bream, mullet, blackfish, whiting, crabs, stingrays and birds like the white-faced heron, oystercatchers, Eastern curlews and many more coming in to feed on the flooded mangrove forest.”
by Kellie Stewart 03 Apr, 2024
Network operators around Australia are breathing a sigh of relief with the launch of Wagners Composite Fibre Technologies' (CFT) new 356mm Fibre Reinforced Polymer (FRP) utility pole. Its launch comes in the wake of rising costs, declining quality and reliability of supply for traditional timber utility poles, due to ‘deforestation and bushfires in 2002 and 2003 which caused large scale destruction of thousands of hectares of hardwood forests.’*  Wagners CFT National Product Specialist - Utilities, James Lorrimer said the new 356mm FRP utility pole is the solution for networks that are finding it near impossible to source larger capacity timber utility poles. “Wagners CFT has worked really hard to expedite the launch of its 356mm utility pole in answer to the call from network operators to find a solution, and quick!,” James Lorrimer said. “The 356 compliments our already existing range of 301mm and 293mm of which we’ve seen some 6,000 poles head out to networks in the past 12 months, thereby taking the pressure off hardwood timber resources for those lighter loads and heights,” Mr Lorrimer said. “But it’s been those bigger loads, bigger capacities where the real need has been and now with the launch of Wagner’s new 356 FRP utility pole, we can offer customers standard service loads to 14m/8kN and 15.5m/5-6kN,” he said. “And with different networks requiring different configurations, just like our 301s and 293s, the new 356s can be custom designed to suit the set up and standard configuration of each network.”
Show More
Share by: