Lateral thinking leads engineers to record breaking bridge

Thinking beyond what you’ve been told is achievable, and proving the impossible is actually possible was inducement enough for a group of engineers at Wagners Composite Fibre Technologies (CFT), to deliver the longest riveted Fibre Reinforced Polymer (FRP) truss bridge in Australia; possibly the world! 

At 18 metres long and 2 metres wide, the heritage green pedestrian bridge now sits unassumingly over an ephemeral creek west of Proserpine on the central Queensland coast; just down from the lawn bowls club on Scottsville Road in Collinsville. 


Wagners CFT Lead Structural Engineer Dr Ali Mohammed said for the tiny township of 1,200, the bridge’s installation was probably fairly uneventful for Collinsville; but for him and his colleagues the bridge represents pushing beyond the threshold of design limitations and challenging long-held beliefs and norms.


“Breaking records is always unique and at 18 metres long the Scottsville Road pedestrian bridge in Collinsville is about 2 metres longer than any other riveted FRP truss bridge in Australia; possibly the world,” Dr Ali Mohammed said.


“It was designed in house here at Wagners CFT by our design team and certified externally by Impact Structural Engineers,” Dr Mohammed said.


“The bridge was pre-assembled at Wagners CFT in Wellcamp before being trucked some 1,100 kilometres up the Leichhardt Highway to Collinsville and craned into place ahead of final installation by local contractors PW Landscapes,” he said.

Tradesman pictured in front of bridge construction smiling.

Pictured - The bridge was pre-fabricated at Wagners CFT in Wellcamp, Qld before traveling some 1,100km to Collinsville, Qld.

Fifteen to sixteen metres has traditionally been the design threshold for a riveted truss bridge like this.


“From a design perspective and at 18 metres, normally we would need to have gone with bolted 125 SHS sections because it's a heavier bridge; heavier in design,” Ali Mohammed said.


“But we have used 125 SHS sections for top and bottom chords and webs and with detailed design checks on serviceability limits, vibrations and riveted connections, we were able to work with Wagners R&D team on the Young’s Modulus of the material and the riveted connections and push the design to 18 metres,” Dr Mohammed said.


“Every FRP truss bridge is challenging to design mainly due to vibration and for this bridge the challenge was to keep the natural frequencies and acceleration ranges within the pedestrians comfort limit according to the design code,” he said.


“This was a big challenge and we achieved this by adopting adequate truss stiffness, considering the elastic modulus of the material being Wagners CFT FRP and the depth of the truss; you want to maintain usability, you don’t want to go so high that you lose aesthetics or usability of the bridge.” 

Pictured - The deck of the new FRP riveted truss bridge is 30mm FRP mini mesh.

Riveted truss bridges are more cost effective because they are lighter and require less material.


“Riveted truss bridges are lighter in weight and easier to build and install compared to bolted truss bridges as they are considered light duty bridges,” Dr Ali Mohammed said. 


“The advantages of using a riveted FRP truss bridge is that it is more cost-effective as you use less material, use lighter connections and its overall lighter weight so it is quicker to fabricate and install,” Dr Mohammed said.


“It still meets the same design load and design life of 100-years, everything else is the same; just the cost for the asset owner and ease of installation is better,” he said.


“I am very proud of this bridge being the longest riveted FRP bridge in Australia because we’ve proven that you do not have to be limited by predetermined boundaries and that providing the numbers add up…it’s possible!”


Meanwhile Owner of PW Landscapes Matt Stokes said a bridge like this is just plug and play for them.


“The design process for us was good and from our perspective it’s made our job very simple; you just have to do an abutment to suit, drop in the edge and then you just have a small two metre tie in,” Matt Stokes said.


“It’s plug and play for us and a fantastic way to do it to minimise the amount of time you are on the work site,” Mr Stokes said.

“It’s the only way to do a pedestrian bridge if you have access for cranage and someone who can pre-fabricate the bridge off site instead of building it over rocks and dust,” he said.


“Time wise it is three to four weeks quicker when you get the bridge built in a workshop at factory rates, in a controlled environment, by a team who work with the product all the time; making it cheaper, more efficient and quicker.”


“Rather than three or so blokes on site for three to four weeks, paying accommodation and meals.”

Popular Flynns Beach in Port Macquarie featuring a Wagners CFT Fibre Reinforced Polymer (FRP) boardwalk.

Pictured - The team at Wagners CT who prefabricated the bridge off site for PW Landscapes.

For waterways the truss bridge is preferred by PW Landscapes because it doesn’t have any foundations that impede natural flood loads.


“The beauty of the truss bridge is that you don’t lose the clearance over the waterway; you don’t impede on water flows underneath,” Matt Stokes said.


“For this creek there’s a whole lot of nothing followed by high flows, it’s not a bad one for us because it disperses over a good spread, but to cope with that high influx of water coming through which usually carries debris with it you don’t want it catching on foundations of the bridge and blocking up the creek,” Mr Stokes said.


“We’ve built a dozen or so single span bridges with Wagners CFT now and this Collinsville Bridge is not our longest overall, but it is our longest riveted FRP truss bridge and a very simple one for us,” he said.

Pictured - Aerial view of the site of the bridge on Scottsville Road in Collinsville near the lawn bowls club.

Pictured - The new FRP bridge replaced an old metal bridge that had been decommissioned.

Share this article:


More stories to explore:

by Kellie Stewart 12 May, 2024
Electricity distribution company, Essential Energy, partners with EV charging company, EVX and Australian manufacturer of Fibre Reinforced Polymer (FRP) structural profiles, Wagners Composite Fibre Technologies (CFT) to trial a streetlight Electronic Vehicle (EV) charger – a new concept for delivering low-impact, accessible EV charging in regional NSW. The prototype streetlight EV charger has been installed in the Mid North Coast town of Port Macquarie to trial an innovative way to increase charging options for residents and visitors to regional, rural and remote communities. The streetlight charger connects to the existing electricity used to power the streetlight, eliminating the need to install additional infrastructure and undergo major earthworks, which is typical for EV charging alternatives, reducing the visual and environmental impact. Due to their convenient location near the curb adjacent to car parking spaces, streetlights have the potential to play a significant role in expanding public ‘top-up’ charging facilities in regional NSW. Essential Energy Chief Commercial Officer Justin Hillier says the trial is using a prototype composite streetlight column with a cavity designed to completely house an EV charger. “Essential Energy has been working in partnership with Wagners CFT and EVX to develop a product that provides a faster and easier way to roll out more EV charging. The innovation of the streetlight EV charger also provides the opportunity for people who live in housing that can’t be retrofitted with charging facilities to purchase EVs, as well as offering top-up charging for tourists and locals. Enabling more options for charging across the Essential Energy network is part of our commitment to facilitating the uptake of electric vehicles.” EVX CEO, Andrew Foster, believes the proof of concept will be great news for local councils across NSW. “By combining innovative technologies with public infrastructure, this new approach to deploying much needed EV chargers allows councils to roll out new public EV chargers easily and cost-effectively at scale and in convenient locations. Importantly, the ability to utilise pre-existing infrastructure instead of adding new electrical assets to the streetscape is anticipated to make it easier for councils to navigate crucial planning considerations, especially when it comes to assessing the public impacts of expanding EV charging capabilities.” Wagners CFT Australia/New Zealand General Manager Ryan Leeson says they look forward to seeing the results of this innovative trial. “As the uptake of electric vehicles and demand for charging increases, Wagners is excited to be partnering with Essential Energy to produce a solution for EV customers that leverages existing infrastructure, is low impact, and uses Wagners proven composite technology in the form of a streetlight column.” Members of the public are encouraged to use the streetlight EV charger, which is free-of-charge, and to provide feedback during the four-week period via a QR code on the side of the column. The streetlight EV charger is located near 1 Clarence Street, Port Macquarie and is available for use until 10 June 2024.
by Kellie Stewart 26 Apr, 2024
Upgrading an old timber boardwalk in an ecologically important mangrove forest that is home to several threatened species and feeds into an internationally recognised marine park is no mean feat! But it’s a challenge like this that New South Wales based Indigenous civil construction company ALI Civil love to take on and pride themselves on successfully delivering. Director Cohen Jirgens said Huskisson Mangrove Boardwalk had reached the end of its useful life but its replacement posed significant challenges to the sensitive environment in which it sat. “The Huskisson Mangrove Boardwalk is located in the Jervis Bay Marine Park in New South Wales Australia and was originally constructed in 1991; and at that time it was 300 metres long and constructed from treated soft and hard woods,” Cohen Jirgens said. “Actually one of the original members of the construction team provided us with some details of the original build including the total cost which was $37,000 for both labour and materials; that works out to be $123 dollars a lineal metre which is totally inconceivable today,” Mr Jirgens said. “Since its construction in 1991, the boardwalk has been a major drawcard for the community of Huskisson attracting tens of thousands of people to gently meander through the established mangrove forest on the tidal mudflat of Currambene Creek,” he said. “And when the tide floods in, the mangroves come to life with bream, mullet, blackfish, whiting, crabs, stingrays and birds like the white-faced heron, oystercatchers, Eastern curlews and many more coming in to feed on the flooded mangrove forest.”
by Kellie Stewart 03 Apr, 2024
Network operators around Australia are breathing a sigh of relief with the launch of Wagners Composite Fibre Technologies' (CFT) new 356mm Fibre Reinforced Polymer (FRP) utility pole. Its launch comes in the wake of rising costs, declining quality and reliability of supply for traditional timber utility poles, due to ‘deforestation and bushfires in 2002 and 2003 which caused large scale destruction of thousands of hectares of hardwood forests.’*  Wagners CFT National Product Specialist - Utilities, James Lorrimer said the new 356mm FRP utility pole is the solution for networks that are finding it near impossible to source larger capacity timber utility poles. “Wagners CFT has worked really hard to expedite the launch of its 356mm utility pole in answer to the call from network operators to find a solution, and quick!,” James Lorrimer said. “The 356 compliments our already existing range of 301mm and 293mm of which we’ve seen some 6,000 poles head out to networks in the past 12 months, thereby taking the pressure off hardwood timber resources for those lighter loads and heights,” Mr Lorrimer said. “But it’s been those bigger loads, bigger capacities where the real need has been and now with the launch of Wagner’s new 356 FRP utility pole, we can offer customers standard service loads to 14m/8kN and 15.5m/5-6kN,” he said. “And with different networks requiring different configurations, just like our 301s and 293s, the new 356s can be custom designed to suit the set up and standard configuration of each network.”
Show More
Share by: